Storage and Handling System
Involved engineering design to install new storage and handling system. A new 15,000 gallon tank, liquid transfer pump and extruder distribution piping completed the system Capital Costs: $500,000 The...
View ArticleNitrogen Inerting System
Addition of a nitrogen inerting system and oxygen monitoring system to two existing railcar loading facilities. Capital Costs: $450,000 The post Nitrogen Inerting System appeared first on APEX...
View ArticleDual Laminate Corzan/FRP Header
Replace a chlorine 24” header with a dual laminate Corzan/FRP header. New header supports for the 300’ system. Capital Costs: $400,000 The post Dual Laminate Corzan/FRP Header appeared first on APEX...
View ArticleExtruder Feed System
Upgrade of an existing 40mm extruder feed system. Added fiberglass and effects feeder along with a downstream side feeder. Capital Costs: $300,000 The post Extruder Feed System appeared first on APEX...
View ArticleDust Collection System
Design of dust collection system for eight extrusion lines. A wet centrifugal collector (crotoclone) was designed to collect nuisance dust from feed throat hoppers and feeders. The project design also...
View ArticleMultiple Powder Silos
Engineering design, start up assistance and programming to add multiple powder silo sources to the existing powder transfer system Capital Costs: $210,000 The post Multiple Powder Silos appeared first...
View ArticleInjection of Liquid Additive
Included the injecting of a liquid additive into the extruder feed throats via the existing catalyst pumps. Modifications to the existing fourth formulation area included a containment dike, a...
View ArticleBi-Component Fiber System
Performed engineering design of a spinning system, staple system and baler system. The above listed equipment was inventoried in a Tennessee plant and relocated to a Georgia plant. The equipment was...
View ArticleFeeder Carousel and Coating Extruder
Performed TURNKEY services for a long glass fiber line. The project consisted of structural steel erection of two platforms, concrete foundations, lighting, firewater, utility piping, central...
View ArticleConsolidation of Manufacturing
Performed preliminary engineering design to consolidate four warehousing/manufacturing sites into a single site. Assistance was provided to the client to provide a time study flow chart. A lean...
View Article